The contract is for the 2020 Esplanade Road Rehabilitation and Neal Dow and 5th Avenue project. The work includes traffic control, clearing and grubbing, installation of a sanitary sewer main, sewer laterals, manholes, modifying existing drainage inlets, constructing curb, gutter, and sidewalk, installing and retrofitting concrete curb ramps, installing electrical conduit, pull boxes and lighting, pavement grinding, HMA paving, and thermoplastic stripes and marking on Esplanade from Eaton Road to 11th Avenue. The scope of work also includes thermoplastic striping and markings removal and replacement, along with application of a slurry seal on the Esplanade from 11th Avenue to Memorial Way. The contract has an engineer's estimate of $3,900,000.00.
• The project involves multiple components, including traffic control, sewer installation, and pavement work.
• The contract has a significant estimated value, indicating a substantial investment in the project.
• The work is expected to be completed on Esplanade from Eaton Road to 11th Avenue, with additional work on the Esplanade from 11th Avenue to Memorial Way.
• The contract has multiple bidders, including Jason Abel, McGuire & Hester, Knife River, Lamon Construction, and Franklin Construction.
• The bid opening date was January 13, 2020, at 4:00 PM.