The University of Wyoming solicited bids for the Central Energy Plant Chilled Water Sump and Tower Expansion project. The project involves installing an owner-supplied cooling tower, condenser pumps, and constructing a sump and equipment vault for the campus chilled water system. The estimated project completion date was March 31, 2022. However, the University of Wyoming has determined to reject all bids submitted for this solicitation.
• The project was scheduled to start after the bid submission date of June 11, 2021.
• A mandatory pre-bid meeting was held on May 21, 2021.
• The University of Wyoming provided various documents, including front-end documents, drawings, specifications, and addenda, for prospective bidders.
• The bid contact, Heather Earl, was available to answer questions and provide information to prospective bidders.