The County of Sacramento is seeking a contractor to construct a municipal groundwater well with a design capacity of 1,800 gallons per minute. The project includes furnishing all labor, materials, and equipment for the construction of the well, including permits, security, conductor casing, and sanitary seal. The borehole depth is approximately 335 feet below ground surface. The contract was awarded to Nor Cal Pump & Well Drilling with a bid of $336,757.00.
• The project requires the construction of one municipal groundwater well with a design capacity of 1,800 gallons per minute.
• The project includes furnishing all labor, materials, and equipment for the construction of the well.
• The borehole depth is approximately 335 feet below ground surface.
• The contract was awarded to Nor Cal Pump & Well Drilling with a bid of $336,757.00.
• The project is located in Sacramento, California.