The contract is for the Cargo Apron Reconstruction and Replacement of Runway 9-27 with a Taxiway at the St. Pete-Clearwater International Airport. The total contract amount is $14,670,617.57, and the project has a Small Business Enterprise (SBE) goal of 10%. The contractor is required to commence work within 60 consecutive calendar days from the date of the Notice to Proceed and complete all work within 315 consecutive calendar days. The key points of this contract include:
• The project involves reconstruction and replacement of a cargo apron and taxiway at the airport.
• The contract has a total value of $14,670,617.57.
• The contractor is required to meet a Small Business Enterprise (SBE) goal of 10%.
• The project must be completed within 315 consecutive calendar days.
• The contractor must commence work within 60 consecutive calendar days from the date of the Notice to Proceed.