This contract is for the setting of eight steel poles and delivering and placing approximately 280 yards of Self-Consolidating Concrete (SCC) near the Arlington Municipal Airport in Arlington, WA. The contractor will be responsible for lifting and setting poles, concrete procurement, concrete pumping, mechanical compaction of concrete, and concrete finishing. The work is expected to be performed at night to minimize disruptions to the industrial center and ensure public safety. The contract was awarded to Olympic Electric Co., Inc. in the amount of $177,500.00, plus tax.
• The contract involves the setting of steel poles and placement of Self-Consolidating Concrete (SCC).
• The work will be performed near the Arlington Municipal Airport in Arlington, WA.
• The contractor will be responsible for lifting and setting poles, concrete procurement, and concrete finishing.
• The work is expected to be performed at night to minimize disruptions and ensure public safety.
• The contract was awarded to Olympic Electric Co., Inc. in the amount of $177,500.00, plus tax.