The contract is for the construction of a Utility Equipment Building at Manchester Meadows Soccer Complex. The project must be substantially completed by April 27, 2024, and finally completed by May 27, 2024. The contract sum is $399,200. The contractor, Ground Thunder Construction Inc., must comply with all applicable federal, state, and local laws and regulations. The contract includes provisions for payment, change orders, warranties, and termination.
• The project involves the construction of a utility equipment building.
• The contractor must complete the project within the specified timeframe.
• The contract sum is $399,200.
• The contractor must comply with all applicable laws and regulations.
• The contract includes provisions for payment, change orders, warranties, and termination.