The Mead Building Condenser Pump Replacement contract involves replacing the existing condenser water pumps with new base-mounted pumps and a parallel piping system at the Mead Building, located at 421 SE 5th Ave, Portland, OR 97204. The contract was awarded to Delta Connects Inc for $125,317.00 USD. The scope of work includes furnishing, removing the existing, and replacing the condenser water pump. The contract duration is approximately 1 year, from 7/15/2019 to 7/15/2020. Key points to consider include:
• The contract requires the replacement of condenser water pumps with new base-mounted pumps and a parallel piping system.
• The contract duration is approximately 1 year.
• The contract was awarded to Delta Connects Inc for $125,317.00 USD.
• The point-of-contact person is Brenda Caldwell, who can be reached at [email protected] or (503) 988-9398.