The City of Sierra Vista has awarded a construction contract to KE&G Construction, Inc. for the State Route 90 Sewer Reroute project. The contract is for a term of 120 days, starting from July 1, 2024, and ending on October 28, 2024. The contract amount is $489,620. The project involves the installation of a new sewer line parallel to an existing sewer line and tying the new sewer line into the existing system. The contractor is required to furnish all labor, materials, equipment, transportation, utilities, services, and facilities required to perform all work for the project. The contract also includes provisions for progress payments, final payment, and warranty. The contractor is required to comply with all applicable federal, state, and local laws and regulations, including those related to non-discrimination and affirmative action.
• The contract is for a construction project to install a new sewer line.
• The project is located in Sierra Vista, Arizona.
• The contract amount is $489,620.
• The contract term is 120 days.
• The contractor is KE&G Construction, Inc.
• The project involves the installation of a new sewer line parallel to an existing sewer line.
• The contractor is required to comply with all applicable laws and regulations.