The contract is for the gymnasium acoustical panel upgrades at 6 schools in the Topeka Public Schools district. The project involves the installation of acoustical panels and banners at each school, with a total base bid for all 6 schools. The contract was awarded to multiple vendors, and the project timeline is estimated to be 10-12 weeks after the first delivery. The key features of the contract include the installation of Tectum Finale wall panels and banners, with a product lead time of 6 weeks to deliver from the date of the bid opening. The project also includes an expedited shop approval process and a total base bid for all 6 schools. Some of the key points to consider for this contract include:
• The contract was awarded to multiple vendors, including Riley Construction Company, Inc., GSR Construction, JP Construction, and Midwest Masonry Construction, Inc.
• The project involves the installation of acoustical panels and banners at each school, with a total base bid for all 6 schools.
• The contract includes an expedited shop approval process and a total base bid for all 6 schools.
• The project timeline is estimated to be 10-12 weeks after the first delivery.
• The contract includes a product lead time of 6 weeks to deliver from the date of the bid opening.