The contract is for the Florin Area New Street Light Project, a Community Development Block Grant project. The work includes pavement trenching, directional boring, installation of underground conduit and conductors, replacement of curb gutter and sidewalk, and installation of street lighting. The estimated construction cost is $500,000. The contract was awarded to M&M Electric Co. with a bid of $1,217,639.00.
• The project is funded by the Community Development Block Grant program.
• The contract requires a General Engineering Contractor, Class A license.
• A pre-bid meeting was held on January 10, 2018, to review M/WBE requirements and provide a project summary.
• The contract documents are available online at www.dgs.saccounty.net/capsd/Pages/Construction.aspx.