This contract concerns the design, engineering, and construction‑administration services required to upgrade the rural power system in the village of Akhiok, Alaska. The awardee is responsible for producing a Conceptual Design Report, detailed engineering designs, and overseeing construction to replace aging underground distribution infrastructure. The work is funded by the Denali Commission (federal assistance) and is performed under a Firm Fixed Price arrangement valued at less than $100 k. The performance period runs from mid‑February 2018 through the end of December 2020, with a construction window for the electrical distribution upgrade slated for May‑October 2019. The contracting agency is the Alaska Energy Authority, and the contract was awarded to CRW.
• Scope: Conceptual design, detailed engineering, and construction‑administration for power system upgrade, including possible separate electrical‑distribution work managed by Kodiak Area Native Association.
• Funding: Denali Commission (federal‑aid) with a contract ceiling under $100 k; payment on a Firm Fixed Price basis.
• Timeline: Bid submission deadline 20 Dec 2018; design work to be completed in time for construction May‑Oct 2019; overall contract period 15 Feb 2018‑30 Dec 2020.