The Upper Cedar Creek Stormwater Improvement Project involves the replacement of two existing corrugated metal pipe culvert crossings with multi-cell reinforced concrete box culverts and drainage channel improvements. The project includes channel grading, berm construction, and large block wall installation. The contract was awarded through an Invitation for Bid (IFB) process, and multiple vendors submitted bids. The project requires the removal of existing structures, excavation, and installation of new stormwater infrastructure. The contract includes a variety of line items, such as mobilization, clearing and grubbing, and installation of asphaltic concrete surface and base courses.
• The project involves the replacement of two existing corrugated metal pipe culvert crossings
• The contract includes a variety of line items, such as mobilization, clearing and grubbing, and installation of asphaltic concrete surface and base courses
• The project requires the removal of existing structures, excavation, and installation of new stormwater infrastructure
• Multiple vendors submitted bids for the project
• The contract was awarded through an Invitation for Bid (IFB) process