The State of Utah - Division of Facilities Construction and Management (DFCM) is requesting bids for the construction of the State Archives HVAC VAV & Controls Upgrade project. The project involves upgrading the mechanical components and replacing the VAV boxes in the State Archives building. The new controls system will be a Niagra N4 open protocol and web-enabled. The construction cost estimate is $158,000. The contract was awarded to one of the three bidding companies: Combustion and Control Service, LLC, Commercial Mechanical Systems & Services Inc., or KHI Mechanical.
* The project involves upgrading the mechanical components and replacing the VAV boxes in the State Archives building.
* The new controls system will be a Niagra N4 open protocol and web-enabled.
* The construction cost estimate is $158,000.
* The contract was awarded through an Invitation for Bid (IFB) process.
* The project has a completion date of 11/01/2024.