The contract is for the Lake Goodwin Relay, Control, and Metering Panels project, which involves the installation of new protective relays to support a new 115kV circuit breaker. The project aims to provide better reliability and protection selectivity at Lake Goodwin. The contract was awarded to Schweitzer Engineering Laboratories, Incorporated, but their proposal was rejected due to conflicts with the District's terms and conditions. The project estimate is $133,000.00.
• The project involves the installation of new protective relays to support a new 115kV circuit breaker.
• The project aims to provide better reliability and protection selectivity at Lake Goodwin.
• The contract was awarded to Schweitzer Engineering Laboratories, Incorporated.