This contract modernizes the Snow Avenue Pump Station for Four Rivers Sanitation Authority in Loves Park, Illinois. It replaces aging bar screens with two high‑capacity channel‑monster grinders, installs overflow bar screens, and upgrades associated electrical and control systems. The scope includes removal of existing manual and automatic bar screens, installation of owner‑supplied grinding units, new metal grating, fire‑stop work, conduit and wiring per NEC Class 1‑Division 1 standards, and full documentation and testing. The project must be completed by 24 Oct 2025, with liquidated damages of $300 per day for late completion. The award is a lump‑sum, full‑open competition contract awarded to Stenstrom Construction Group.
• Removal of existing bar‑screen equipment and installation of two channel grinders + overflow screens
• Electrical work: new conduit, wiring, breakers, control panels, E‑Stop stations, SCADA integration
• Owner‑supplied equipment must be packed, shipped, and installed; contractor provides all civil, mechanical, and electrical labor
• Strict outage limits (≤ 60 min per outage) and 48‑hour notification for emergency shutdowns
• Requires 10 % bid bond, 100 % performance & labor‑material bonds, and extensive insurance coverage.