This Design-Bid-Build project involves the demolition of an existing condemned US Navy pier and the construction of a new pier for four Offshore Patrol Cutters (OPCs), along with a new bulkhead, laydown area, parking, stormwater management, fire/potable water, electrical, telecommunications, and compressed air utilities. The project will be constructed at Naval Station Newport, Rhode Island. The contractor will be required to perform the work within 918 calendar days, including the 15 calendar days for submission and approval of performance and payment bonds after the contract award. The contractor must also provide a signed Project Labor Agreement with their Price Proposal submission.
• Demolition of an existing condemned US Navy pier (1,570 feet long x 100 feet wide)
• Construction of a new pier (1,000 feet long x 80 feet wide) for four Offshore Patrol Cutters (OPCs)
• Construction of a new bulkhead (360 feet long)
• Laydown area, parking, stormwater management, fire/potable water, electrical, telecommunications, and compressed air utilities
• Performance period: 918 calendar days
• Required to submit a signed Project Labor Agreement with Price Proposal submission