The California State University, Fullerton is soliciting sealed‑bid proposals for the design‑build construction of a new pedestrian bridge (“Titan Gateway”) over Nutwood Avenue at Commonwealth Avenue. The project includes a single‑span prefabricated steel truss bridge, cast‑in‑place abutments on pile caps, retaining walls, approach ramps, roadway and parking lot modifications, traffic‑signal relocation, site work, landscaping, and lighting. The work is funded by federal, state, university, and county sources and must comply with Davis‑Bacon prevailing‑wage rules, Buy‑America requirements, and a minimum 3 % DVBE participation.
• Scope covers structural steel fabrication, concrete foundations, civil site work, utilities, traffic‑signal installation, lighting, landscaping, and associated permitting.
• Mandatory pre‑bid conference on 17 Mar 2026; revised bid deadline now 5 May 2026.
• Contractor must be pre‑qualified, hold a California “A” license, be DIR‑registered, provide $10 M insurance, and submit DVBE documentation within 24 hours after bid due date.
• Estimated construction cost is $11.8 million; project duration is approximately 547 calendar days from notice to proceed.