The Ohio Department of Natural Resources is seeking a qualified contractor to replace the floor system of the Mohican State Park cable‑suspended pedestrian bridge and perform miscellaneous rehabilitation. The work includes removal of existing decking, installation of new structural steel or optional FRP members, placement of HDPE deck panels, timber tower treatment, cable and turnbuckle replacement, erosion control, and related site utilities. The contract is a single‑prime general contract with a base value of $123,030 and an optional FRP alternate of $17,385, total potential award up to roughly $140k. The project must be completed within 155 calendar days, targeting substantial completion by 30 Mar 2027. The contractor must provide a digital ID, bid guaranty, EDGE participation (5 % goal), and comply with state prevailing‑wage, SUPR, and OSHA requirements.
• Scope: floor‑system replacement, deck panel installation, structural steel/FRP member installation, cable and turnbuckle work, erosion control, timber treatment.
• Contract value: $123,030 base, $17,385 optional FRP alternate (≈ $140k total).
• Schedule: bid deadline 2 Sep 2026; work to start approx 26 Oct 2026; complete by 30 Mar 2027 (155 days).
• Requirements: electronic bid via BidExpress, Digital ID, bid guaranty, EDGE program participation, prevailing‑wage compliance, safety & environmental plans.