The Texas A&M University System Office of Facilities Planning & Construction is soliciting proposals for the RELLIS Water Tower project in Bryan, Texas. The project includes the construction of a 0.75 Million Gallon Composite Elevated Storage Tank, demolition of an existing tank, and associated site work. The project also includes the installation of water lines, sanitary sewer lines, pressure reducing valve vaults, and electrical, instrumentation, and controls.
• 0.5 MG EST
• EST Demolition
• ~400 LF of 16” HDPE Water Line
• ~900 LF of 6”/12” HDPE Sanitary Sewer
• Pressure Reducing Valve Vaults
• Drainage Improvements
• Electrical, Instrumentation, and Controls
• Associated Site Work.