The City of Fayetteville is soliciting sealed bids to rehabilitate Taxiways F (Foxtrot) and G (Golf) at Fayetteville Regional Airport. The work includes full‑depth removal of existing asphalt, cold‑milling, placement of millings, new aggregate base, asphalt surface and leveling courses, extensive lighting and signage replacement with LED fixtures, underground power‑cable installation, and complete pavement marking. The project is funded with FAA Airport Improvement Program (AIP) dollars and must comply with FAA Buy‑American preferences, Davis‑Bacon wage rules, and strict night‑only runway‑closure constraints for one five‑day phase.
• Civil works: removal of up to 9‑in. asphalt, cold‑milling ≈ 24,770 sq yd, new asphalt ≈ 8,470 tons, base course, prime/tack coats, and restoration (seeding, sod, mulch).
• Electrical works: installation of ~89 LED edge lights, LED signs, underground conduit, power cable, ground rods, and CCR recalibration (allowance $15,000).
• Schedule: 110 calendar‑day contract, with a 5‑day night‑only runway closure, 45‑day non‑AIP civil phase, and a 15‑day additional phase.
• Mandatory pre‑bid conference on June 16, 2026; bids due July 16, 2026; performance and payment bonds required at 100 % of contract amount.