The Santa Clara Valley Water District is seeking a qualified concrete contractor to construct a new cast‑in‑place concrete spillway and two concrete headwalls at the Page Ditch site in Campbell, CA. The contractor will supply all labor, materials, reinforcement, equipment, and related services needed to complete the concrete work, while Valley Water will handle grading, excavation, water control, HDPE piping, and slide‑gate installation. Work must be performed on weekdays between 8:00 a.m. and 5:00 p.m., coordinated with the Valley Water Project Manager, and completed in compliance with all applicable federal, state, and local regulations. A mandatory pre‑bid site visit is scheduled, and a 10 % bid bond (e‑bond) is required. The contract value is estimated between $186,500 and $211,000, with a 31‑day construction schedule and liquidated damages of $250 per day for delays.
• Construct one cast‑in‑place concrete spillway and two concrete headwalls (approx. 25 ft × 20 ft × 0.5 ft spillway; two 10 ft × 35 ft × 1 ft headwalls).
• Provide all reinforcement, formwork, concrete mix design, placement, quality‑control testing, dust suppression, and debris disposal.
• Coordinate daily with Valley Water, adhere to safety and environmental requirements, and submit progress reports, as‑built documentation, and final certifications.