The project involves replacing site underground chilled water piping at the VA Medical Center in Tennessee. The work includes demolishing existing piping, installing new piping, and connecting it to existing chilled water lines. The project is divided into phases, and the contractor will be responsible for developing and implementing the phasing sequences. The project requires coordination with the owner and other stakeholders to ensure a smooth shutdown and re-establishment of chilled water flow to the buildings.
• The project includes installing new 12" underground piping and flushing loops in the tunnel/storage room and B119 area.
• The contractor must schedule chilled water shutdowns with the VA and other stakeholders.
• The project requires demolishing existing pipe and connecting to new piping.
• The contractor must open isolation valves and re-establish chilled water flow to the buildings.
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.