The Houston County School District (HCSD) is soliciting qualified construction firms to serve as Construction Manager at Risk (CM‑at‑Risk) for extensive renovations and modifications of two elementary schools (Quail Run and David A. Perdue). The total project budget is $10 million ($5 million per school). Work must be performed primarily during nights, weekends, school holidays, and the summer break (April – August 2027) with punch‑list completion by December 1 2027. The CM‑at‑Risk will be responsible for pre‑construction services, procurement of at‑least three bids per trade package, bonding, insurance, compliance (IRCA, local statutes), and overall construction management through to warranty. The contract will be awarded after a proposal evaluation, possible interviews, and negotiation, with a notice to proceed expected in November 2026.
• Scope: Interior demolition, finish replacement, MEP upgrades, minor exterior work, and site work for two K‑12 elementary schools.
• Delivery method: Construction Management at Risk with a Guaranteed Maximum Price (GMP).
• Budget: $10 M total (approximately $5 M per school).
• Schedule: Pre‑construction Nov 2026 – Feb 2027; Construction Apr 2027 – Aug 2027; Punch‑list complete by Dec 1 2027.
• Mandatory pre‑proposal conference: Sep 23 2026, Warner Robins, GA.
• Submission requirements: 6 hard copies + 1 electronic PDF, sealed, marked per instructions; no electronic‑only submissions.
• Evaluation criteria include firm overview, management team, relevant experience, approach to CM‑at‑Risk, financials, fees, and local participation.
• Required bonds/insurance: 100 % payment and performance bonds, comprehensive liability and workers’ compensation coverage.