This project entails a comprehensive rehabilitation of Water Plant No. 2 for Harris County Municipal Utility District No. 391. The scope covers interior and exterior blast‑cleaning, priming, and coating of multiple ground storage and hydro‑pneumatic tanks, installation and operation of de‑humidification equipment, replacement of tank accessories (vents, ladders, roof hatches, rafters), emissions control, full disinfection and bacteriological sampling, roof‑structure replacement, patch welding repairs, and pit filling. The work must be completed within a 120‑day construction window plus a 30‑day close‑out period, totaling roughly five months of field activity. Three qualified contractors have submitted bids, with the lowest apparent bid at $990,000 and the highest at $1,276,500.
• Scope includes full‑scale tank surface preparation, coating, and associated mechanical/structural repairs.
• Project duration is approximately 150 calendar days (120‑day construction schedule plus 30‑day close‑out).
• Bid submission deadline was September 10, 2026; pre‑bid conference (non‑mandatory) held on September 4, 2026.
• Three bidders: W.W. Payton, D&M Tank, LLC, and Pardalis Industrial Enterprises, Inc.
• No award date disclosed; contract value expected between $990 k and $1.28 M.