The New York State Office of General Services is seeking qualified contractors to replace the boiler control system, associated motors, VFDs, and electrical distribution for the powerhouse (Building 21) at Riverview Correctional Facility in Ogdensburg, NY. The work includes complete demolition of existing boiler controls, installation of new control panels, variable‑frequency drives, motor starters, updated instrumentation, and the necessary electrical wiring, conduit, and grounding to meet current NYS and NFPA codes. The contract also requires completion of pre‑functional checklists, functional performance testing, and submission of as‑built documentation.
• Remove existing boiler control panels, pumps, fans, and related piping/instrumentation.
• Install new BLR‑1 to BLR‑5 control panels, BOP and BMS panels, VFDs, motor controllers, and associated SCADA/HMI hardware.
• Provide all new electrical work: conduit, panelboards, breakers, grounding, and compliance with 2025 NYS Energy Code, 2025 Uniform Building Code, NEC 2023, and NFPA 85.
• Conduct mandatory pre‑bid site visit on 08/20/2026 and complete required pre‑functional and functional testing documentation.
• Estimated project cost between $50 k and $100 k; bid deposit $7,100 required.