The Tarrant Regional Water District (TRWD) seeks qualified contractors to install AASHTO‑compliant safety signage and rumble strips along the Clearfork branch of the Trinity River Trail in Fort Worth, Texas. TRWD will supply all signposts, weld plates, and safety signs; the contractor is responsible for labor, footers, attachment, rumble‑strip installation, safety planning, trail closures, and progress reporting. The contract is valued over $50,000, requires a 2 % bid bond, and must be completed by March 19 2027. Proposals are due September 23 2026, with questions due September 21 2026 and award expected October 20 2026.
• Scope: Install signage and rumble strips, pour footers, attach pre‑welded signposts, develop trail‑closure and safety plans.
• Location: Clearfork branch of Trinity River Trail, between HW 183 and the Westfork junction; separate phase between W 7th St bridge and I‑30 bridge.
• Timeline: Proposal due 9/23/2026; award 10/20/2026; work to be finished by 3/19/2027 (≈5 months).
• Evaluation: 40 % price, 30 % experience/qualifications, 20 % project approach, 10 % schedule. Minimum 3 similar projects required.
• Requirements: 2 % bid bond (if >$50k), insurance, performance bonds, various compliance forms, weekly progress updates.
• Contact: Claire Killough, Purchasing Supervisor (
[email protected], (817) 991‑8992).