The Gwinnett County Board of Commissioners is seeking a contractor to replace the existing apron at the Gwinnett County Police Aviation Hangar. The work consists of full demolition of the current asphalt and concrete surface, followed by placement of a new concrete apron that meets FAA safety standards. Bidders must provide a 5 % bid bond, 100 % performance and payment bonds, and comply with FAA Advisory Circular 150/5370‑2G, including detailed night‑lighting and safety plans. The contract will be awarded to the lowest responsive and responsible bidder, with no options for alternates.
• Demolition of existing asphalt and concrete apron, removal of tie‑downs, trench drains, and underground piping.
• Installation of a new concrete apron (fiber‑mesh reinforced, no rebar) with a maximum 1 % slope transition to existing asphalt.
• Required compliance with FAA AC 150/5370‑2G, including a 4‑week concrete cure period, barricade standards, dust/FOD control, and night‑lighting plan approval.
• Mandatory bid documents: original + two copies, signed acknowledgment on page 000410‑3, 5 % bid bond, and, for out‑of‑state firms, Georgia authority to do business.
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.