The Oregon Department of Transportation is seeking a qualified contractor to replace bridge piles on the Yaquina Bay Bridge as part of the Major Bridge Maintenance project. The work includes all labor, materials, transportation, equipment, permits, and services necessary for the completion of the project. The project is expected to start on November 1, 2025, and be substantially completed by February 15, 2026, with a final completion date of February 27, 2026. The project has an estimated cost of $1,000,000 to $2,000,000 and is funded by the State of Oregon. The contractor will be required to comply with the State Buy America provisions, which require that certain materials, including steel and iron products, be produced in the United States.
• The project includes replacing bridge piles as shown in the attached documents.
• The contractor must comply with the State Buy America provisions.
• The project has an estimated cost of $1,000,000 to $2,000,000.
• The project is expected to start on November 1, 2025, and be substantially completed by February 15, 2026, with a final completion date of February 27, 2026.
• The contractor will be required to provide a certificate of materials origin before incorporating certain products or materials into the project.