The State of Delaware is seeking qualified contractors to replace the existing cooling tower at the Transportation Management Center in Smyrna. The work includes demolition of the existing tower, installation of a new induced‑draft cooling tower, associated mechanical and electrical modifications, and two required shutdowns of the condenser‑water loop. All work must be completed so the system is operational by March 15 2027, with a $10,000 allowance for unforeseen conditions and mandatory bonding and insurance requirements.
• Remove existing cooling tower and isolation valves; install new tower, piping, breakers, and disconnects.
• Perform two scheduled shutdowns of the condenser‑water loop and a two‑week pre‑demolition shutdown for performance data.
• Provide a temporary tower at no extra cost if the new tower is not operational by March 15 2027; adhere to prevailing‑wage rates and submit required bid bonds (10 % of bid).
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.