The contract is for the furnishing and delivery of two each backwash pumps and associated valves for the Wailua WWTP. The contract was awarded to Hawaii Engineering Services, Inc. for a total price of $22,832.18. The contract is to be completed within 120 calendar days of the official commencement date. The scope of work includes the delivery of two each backwash pumps, air release valves, ball check valves, and knife gate valves, complete as specified.
• The contract is for a specific project, namely the Wailua WWTP.
• The contract includes the delivery of various valves and pumps.
• The contract has a specific completion date and duration.
• The contract was awarded through a competitive bidding process.
• The contract includes requirements for final payment, including tax clearance compliance and a contractor's certificate of compliance.