The contract is for an emergency change order to add funding to the current annual sewer rehab and repair contract with Rowland Inc. to resolve a water main conflict identified on the City of St. Pete Beach's Drainage Project. The work involves a 6-inch offset of the potable water main located at 41st Ave. & Belle Vista. The contract is valued at $36,963.80 and is scheduled to begin on March 15, 2021. Key points include:
• The contract is an emergency change order to address a water main conflict
• The work involves a 6-inch offset of the potable water main
• The contract is valued at $36,963.80
• The work is scheduled to begin on March 15, 2021
• The contract is with Rowland Inc., who is already on-site at the location and can resolve the conflicts by offsetting the water main in two different locations.