The contract is for the replacement of the HVAC system at Suncoast Elementary School. The project includes the construction of a new chiller yard, installation of new outdoor rated air handling units, and underground chilled water distribution piping. The contract was awarded to Air Mechanical & Service Corp. for $904,223. The project is expected to be completed within a few months, starting at the beginning of Summer 2021 and finishing by the start of the 2021-2022 school year.
• The project is funded by Half-Cent Sales Tax proceeds.
• The contract includes the purchase of goods and services for the project.
• The Hernando County School Board is responsible for the project and published the bid.
• The points of contact for the project are Rick Thoma, Brian Ragan, and Jim Lipsey.