The County of Sacramento is seeking bids for the construction of a new Heavy Equipment Maintenance Building (HEMB) at the Sacramento Regional Wastewater Treatment Plant. The project includes the construction of a 6,400 square-foot building with various features such as an office, break room, restrooms, compressor/lube room, parts storage, tool storage, two drive-through bays, press area, welding area, tire repair shop area, and mezzanine for storage. The project also includes a covered storage area, miscellaneous site improvements, and the relocation of equipment and supplies from the existing HEMB to the new HEMB. The engineer's estimated construction cost is $5,859,000.
• The project requires a General Engineering Contractor – Class A license.
• The bid date was March 16, 2017, at 2:00 pm.
• The contract documents were available at the County of Sacramento offices.
• A mandatory pre-bid conference and walk-through were held on February 22, 2017.