The 2018 Irrigation Extension Project involves the extension of irrigation piping across city streets and on University of Wyoming property. The project includes pot-holing and drilling, installation of sleeves, piping, valves, fittings, appurtenances, and tie-ins. The estimated project completion date is November 15, 2018. The contract was awarded to AAA BUILONG SERVICES, with a total construction cost of $971,514.00. The project also involves several subcontractors, including TEUPLE CONST, SIMON CONST, MARTIN MIRETTA, and DENVER BRASS SUPPLY.
• The project requires horizontal drilling and trenching to install irrigation piping.
• The contract includes a base bid and an alternate bid.
• The project has a mandatory pre-bid meeting and a walk-through.
• The contract requires a bid bond and a certified copy of power of attorney.
• The project has a completion date of November 15, 2018.