The City of Palm Bay, Florida, awarded a contract for the replacement of culverts on C-75 at Pembroke, Emerson, and Pebble. The contract involves the removal, disposal, replacement, and restoration of three separate culvert crossings, including all associated work such as maintenance of traffic, erosion control, and final cleanup. The contract was awarded to Gregori Construction for an amount of $842,140.53. Key aspects of the contract include:
• Replacement of existing failed culverts with new box culverts
• Associated work such as excavation, dewatering, demolition, and disposal of unusable materials
• Maintenance of traffic and traffic detours
• Erosion control and final cleanup
• Procurement and installation of selected structures
• Utility conflict coordination and relocations