The contract involves the replacement of the roof at the Summit County Engineer's Vehicle Maintenance Facility, located at 601 E. Crosier St., Akron. The project includes removing and replacing approximately 200 square of shingle roofing. The engineer's estimated cost of the project is $125,000.00. The contract was awarded to M&C Siding and Roofing, LLC, with a total price of $73,562.50. Some key aspects of the project include:
• Replacing deteriorated roof sheathing
• Replacing rusted storm collar at vent stack
• Replacing rusted vent stack from first joint under roof deck
• Removing and replacing shingle roofing as per plans and specifications
• Compliance with prevailing wage requirements
The contract requires the vendor to provide a bid bond and to upload a copy of the signed Successful Bidder Requirements Forms. The vendor must also attend a mandatory pre-bid meeting at the project site.