The University of Missouri Western is replacing the steam‑boiler system in the Blum Union Student Center. The scope includes demolition of the existing boiler, feed tank, steam heat exchanger, and storage tank, followed by installation of two 25 HP vertical low‑pressure steam boilers, two 500,000 BTU condensing water heaters, associated feed‑water tanks, piping, flues, pumps, emergency stop controls, and full commissioning and owner training. The work must be completed within a five‑day window in late November 2025, with prevailing‑wage compliance, a 5 % bid bond, and standard university insurance requirements.
• Removal of existing boiler and related equipment, then supply and install new high‑efficiency boilers, water heaters, tanks, and ancillary piping.
• Mandatory compliance with Missouri prevailing‑wage laws, E‑Verify enrollment, and a notarized work‑authorization affidavit for bids over $5,000.
• Single‑source award to RS Industrial Services at a winning bid of $298,240, with project start Nov 24 2025 and completion Nov 29 2025.