The State of Utah - Division of Facilities Construction and Management (DFCM) is requesting bids for the construction of the Richfield Administration Building Generator Replacement project. The project involves replacing the emergency generator and automatic transfer switch, as well as adding a docking station. The construction cost estimate is $350,000.00. The contract was awarded to four vendors: CTI Companies, LLC, Prime Power and Electric, Landmark Companies, Inc., and Endless Energy Electric Inc. The vendors will be responsible for completing the project by the completion date of 06/30/2025.
• The project involves replacing the emergency generator and automatic transfer switch
• The project involves adding a docking station
• The construction cost estimate is $350,000.00
• The contract was awarded to four vendors
• The vendors will be responsible for completing the project by the completion date of 06/30/2025