The contract is for the construction of the Anderson Groundwater Treatment Plant, which includes a CMU 66 foot x 66 foot building with architectural features, HVAC, plumbing, drains, electrical and controls. The treatment processes include two parallel horizontal pressure filters with GreensandPlus media and onsite sodium hypochlorite generation. The site work includes landscaping, grading, drainage, fencing, security and lighting for the entire Well 16/Anderson WTP Site. The project also includes relocating the existing generator and two 10 foot diameter by approximately 70 foot long cylindrical FRP underground water storage tanks.
• The project is sized for up to 6,000 gpm.
• The yard piping includes approximately 420 feet of 8-inch to 24-inch stormdrain, 160 feet of 6-inch sewerline, and 225 feet of 24-inch raw and finished waterline.
• All sewer and water services will need to remain in-service for the duration of the project.
• The neighboring sites will need to be protected as further noted in the plans and impacts minimized to the extent practicable.