This contract concerns the replacement of generator main leads for all eight units at Rock Island Powerhouse 2, a critical component of the Rock Island Dam’s hydroelectric generation system. The work is a progressive design/build effort, requiring removal of existing generator leads, installation of new leads, testing, and certification to ensure reliable operation. The solicitation was issued by Chelan Public Utility District and attracted multiple electrical contractors, but the award was ultimately given to Olsson Industrial Electric, Inc. The project’s estimated budget is roughly $5.2 million, reflecting the scale and technical complexity of the work at a major hydro‑electric facility.
• Scope: Replace generator leads for 8 turbine units at Rock Island Dam Powerhouse 2.
• Awarded Vendor: Olsson Industrial Electric, Inc. (single‑award).
• Agency: Chelan Public Utility District (Washington).
• Estimated Value: $5,200,000 (ballpark).
• Procurement: Full and open competition via RFQ (20‑18) with multiple respondents.