The City of Houston’s Houston Airport System awarded a single‑award contract to PRCHOU, LLC for the reconstruction of approximately 580 linear feet of Metro bus drive lanes beneath the Red Parking Garage and along the Hobby Airport Loop at William P. Hobby Airport. The work is divided into five construction phases and includes demolition, lime‑treated sub‑grade preparation, placement of jointed reinforced concrete pavement, curb & gutter work, traffic‑control planning, storm‑water management, and the replacement of in‑roadway lighting and related electrical infrastructure. The contract is a 180‑day, time‑is‑of‑the‑essence agreement with liquidated damages of $800 per day for delays and includes the usual performance, payment, and maintenance bonds.
• Scope: demolition of existing pavement, lime‑treated base, new concrete pavement, curb & gutter, markings, signage, and electrical lighting.
• Schedule: 180‑day contract period beginning 13 Oct 2021, ending 11 Apr 2022; bids were due 6 May 2021.
• Financials: awarded contract amount $479,472; 10 % security deposit required; performance and payment bonds at 100 % of contract price.