The Rio Vista Water Treatment Plant Clearwell No. 1 Improvements Project involves modifications to a 15 million gallon treated water clearwell, including demolition and removal of a geomembrane liner, baffles, and floating cover, as well as installation of drain pipes, liner leakage collection pipes, concrete anchor curbs, geomembrane liner, baffles, and floating cover. The project also includes installation of a water quality monitoring system and guardrails, modifications to existing access platforms, and restoration of existing asphalt pavement. The contract was awarded to the lowest responsive and responsible bidder, with the apparent low bidder being Erosion Control Applications, Inc. with a total base bid price of $3,588,750.00.
• The project involves federal funding and therefore bidders must comply with federal requirements.
• A mandatory pre-bid conference was held on July 29, 2014, at 10:00 A.M. at RVWTP Administration Building.
• The bid opening was held on September 3, 2014, at 2:00 PM.
• The contract documents include bid specifications, bid drawings, and addenda.