This contract concerns the replacement and upgrade of HVAC equipment on Badger Drive. The scope includes removal and disposal of existing boiler and air‑handler units, furnishing and installation of new boiler and air‑handler, integration of the new equipment with the building management system, and full testing and certification of the installed system. The bid opening is scheduled for January 31 2025 at 11:00 AM CST, indicating a competitive single‑step procurement process. While individual line‑item prices for the new equipment total $58,490, the document also shows higher aggregate bid totals (up to $182,860) suggesting additional costs such as disposal fees, taxes, and vendor mark‑ups. No award decision is presented, so the eventual vendor(s) remain unknown.
• Replacement of boiler and air‑handler with new units (unit prices $16,710 and $38,280).
• Rework of the building management system to interface with the new equipment ($2,500).
• Testing and certification of the installed HVAC system ($1,000).
• Competitive bid opening scheduled for 01/31/2025, administered by the City of Waukesha, Wisconsin.