This bid tabulation details the competitive bidding results for the “Horeb Springs Retaining Wall Improvements” project, a municipal‑level construction effort focused on constructing a new Redi‑Rock retaining wall, associated site work, and ancillary improvements such as sidewalk replacement, stair and railing replacement, and safety barrier reinstatement. Two firms submitted bids, with All‑Ways Contractors, Inc. offering a base‑bid total of $488,906 and Lowe Underground, Inc. proposing $676,580. Mandatory alternates for repairing or fully replacing the existing retaining wall are also included. The scope includes extensive excavation, concrete work, and the installation of a sizeable rock‑fill retaining wall (2,820 sf). No award decision or contract number is present in the provided excerpt.
• Core work: new 2,820 sf Redi‑Rock retaining wall plus excavation, site staging, sidewalk and colored‑concrete replacement.
• Mandatory alternates: repair/renovate (500 sf) and replace (details truncated).
• Competitive bids: All‑Ways (≈$489 k) vs. Lowe Underground (≈$677 k).