The contract is for the installation of an electric bus charging system at the Nevada County Operations Center (NCOC). The system consists of a ChargePoint 150kW Express Plus plug-in charging system, which includes a Power Block charging power supply cabinet and a Power Link dispenser cabinet. The contractor is responsible for installing the system, including connecting it to the existing electrical infrastructure and installing concrete equipment pads and bollards. The contract also includes the removal of existing striping and the painting of new parking stripes. The engineer's estimate for the contract is $240,000.
• The contract duration is 40 working days.
• The contract is funded by the California Air Resources Board and the U.S. Environmental Protection Agency.
• The contract includes a bid bond requirement.
• The contract has a DBE (Disadvantaged Business Enterprise) goal of 2% for MBE (Minority Business Enterprise) and 1% for WBE (Women Business Enterprise).