Houston Airport System seeks a contractor to remove the existing Precision Approach Path Indicator (PAPI) system at Ellington Airport (EFD) and install four new FAA‑compliant LED PAPI Type L‑880(L) units. The scope includes providing all labor, supervision, tools, testing, and incidentals required for removal and installation. Houston Airport System will furnish the LED equipment; the contractor must reuse existing foundations and infrastructure, does not need to obtain a site visit or security badge, and must operate under an informal bid process.
• Removal of existing PAPI equipment and installation of a four‑unit LED PAPI system (L‑880(L)).
• Contractor provides labor, supervision, tools, testing, and incidentals; equipment is supplied by the agency.
• No site visit, no badging/escort requirements; existing foundations reused; deadline for bid submission June 6, 2026.