The contract is for the installation of a semi-permanent/temporary netting/fabric under the existing ceiling grid and tile throughout the designated areas in Terminal and Concourse A at the Sacramento International Airport. The project has an engineer's estimate of $175,500.00 and requires a CA Contractor License with a Class A certification. The contract was awarded to Western Exterminator Company for $174,500.00. Key aspects of the project include:
• Installation of netting/fabric under the existing ceiling grid and tile
• Location: Sacramento International Airport Terminal and Concourse A
• Engineer's estimate: $175,500.00
• CA Contractor License Required: Class A
• Awarded to Western Exterminator Company for $174,500.00