This contract awards the design‑build construction of non‑standard taxiway improvements at William P. Hobby Airport, addressing runway incursion issues and bringing the airfield into FAR‑139 compliance. The work includes demolition of existing taxiways, extensive earthwork, drainage installation, sub‑grade preparation, paving (asphalt and concrete), lighting, signage, and pavement markings across multiple taxiway intersections. The project is funded partially by an FAA Airport Improvement Program grant and requires an 11 % DBE participation goal, a 10 % bid security, and compliance with Davis‑Bacon prevailing‑wage rates.
• Scope: demolition, excavation, embankment, drainage, sub‑grade, paving, electrical, lighting, signage, and marking for several taxiway segments.
• Schedule: 18‑month contract period (estimated) with a start after award (Sept 2023).
• Financial: $42.69 million contract value; $300 k cash allowance; 10 % bid security; full performance, payment, and maintenance bonds required.