The University is restoring the fire‑damaged Biological Science Building laboratory spaces on its Detroit campus. The work includes full demolition of damaged finishes, replacement of MEP systems, installation of new laboratory casework, equipment, finishes, and fire‑protection upgrades, all to BSL‑2 standards. The contract is a lump‑sum, competitive bid, with a $1.2‑$1.6 M construction budget, required compliance with the WSU wage schedule, extensive safety and environmental controls, and a substantial‑completion deadline of 30 June 2025.
• Complete interior demolition and reconstruction of ~1,900 GSF of BSL‑2 labs.
• New HVAC, plumbing, electrical, fire‑sprinkler, and laboratory casework installations.
• Mandatory WSU prevailing‑wage rates, 5 % bid bond, 100 % performance/labor‑payment bonds, and $100/day liquidated‑damages for late completion.
• Awarded to LaSalle Group; all submissions were electronic via the university’s bid portal.