This solicitation seeks a qualified contractor to replace the existing Automatic Transfer Switch (ATS) controller for the generator at the Wilmington Police Headquarters. The work must use the existing ATS enclosure, wiring, and piping, and be completed with minimal disruption to police operations, limiting power outages to no more than two consecutive hours. The contractor must provide a factory‑trained service technician, perform load‑transfer testing, and train police department staff. The project requires compliance with strict safety, insurance, and minority‑business participation requirements, and all work must be performed after normal business hours or on weekends.
• Scope: removal of existing ATS controller, installation of new controller, wiring termination, testing, and training.
• Schedule constraints: power outage ≤ 2 hours; work after hours/weekends; start within 10 days of order.
• Mandatory pre‑bid meeting on April 8 2025; bid submission deadline April 22 2025, 3 PM EST.
• Evaluation based on responsiveness, price, ability to meet outage limit, MBE/DBE participation (≥ 14 %), and insurance compliance.